    108 Street Industrial – Corridor Rehabilitation

    108 Street, Westlock, AB

    Project Description: This project was comprised of upgrading the roadway, underground infrastructure, and curb/sidewalks along 108 Street. To accomplish this required the removal of the existing road surface and curb/sidewalks, installation of new sanitary water main, installation of new roadway structure, installation of new curbs and sidewalks.  

    Grants, Funding Source: Funding approved through 2020-2024 Capital Plan. 

    Partners: MPE Engineering Ltd. and Knelsen Sand & Gravel

    2021 Project Wrap Up:

    • Phase One of this project, 97 Avenue to the Bulk Water Station, was completed in November 2021, including the first lift of asphalt. 
    • The 108 Street Bulk Water Station was back in operation effective November 22, 2021.
    • Start Date: April 6, 2021
    • Anticipated Completion Date for Phase One:  November 2021


    Phase Two continues the project from the Bulk Water Station to CN Rail.

    Anticipated Start Date for Phase Two: TBA

    Anticipated Completion Date for Phase Two: TBA