Capital Project Phases
- Concept: This is the first phase of a project where a project is presented to council that will significantly improve infrastructure or a Town facility.
- Development Design: During this phase of the approved project, drawings and cost estimates are developed. The goals and objectives of a project are identified to maximize service delivery in our facilities and infrastructure.
- Detailed Design: During this phase, the concepts and design ideas are further developed and refined into detailed plans and specifications. Engineering analysis may ensure the feasibility of the project, safety and compliance with codes and regulations. This phase happens before a project is tendered and lays the foundation for successful project execution.
- Build: Includes construction and implementation of a project. It involves managing resources, coordinating contractors and suppliers, conducting inspections and ensuring the project is completed within schedule and budget.
- Operate: This is the final phase after construction or implementation is complete. It involved ongoing management, maintenance, and utilization. This phase focuses on optimizing performance, monitoring costs and addressing any operational issues that may arise.
East Glen Park Inclusive Playground (Old Water Tower)
This will be designed as a barrier-free, accessible playground that will provide fun for families all year round. There are opportunities for this project to expand if grant submissions are successful.
Status: Detailed Design
More information is available on the Playground for All feature page.
93 Street (99-102 Ave) & 99 Ave (93-94 St)
Southview Subdivision
93 Street will be extended West into Southview to allow for future residential development.
Status: Operate
107A Avenue – Corridor Rehabilitation
Storm, water and sewer replacement.
Status: Build
Completion Date for Phase One: October 2024
Phase Two of construction will commence Spring 2025
View or Download More Details about 107A Avenue
Aspendale Dry Pond Drainage Correction
Asphalt and drainage improvements from 110 Avenue to 103 Street.
Status: Development Design
Bulk Water Station Building and Grounds Improvements
Drainage improvements and paving of the parking lot.
Status: Development Design
Fire Hall Rehabilitation Program
Upgrades to the facility will include overhead and exterior door replacement, exhaust system replacement, HVAC, electrical and flooring replacement, washroom renovations and concrete replacement outside of the overhead doors.
Status: Build
Westlock Rotary Spirit Centre Parking Lot Expansion
(Formerly Jubilee Arena Demolition & Land Reclamation)
The site of the old Jubilee arena will be reclaimed and turned into a multi-use parking lot complete with power. This site will provide extra parking for the Spirit Centre and can be used for outdoor markets and event space.
Status: Build
Completed Capital Projects
Dry Sauna
The steam room at the Westlock Aquatic Centre was converted into a dry sauna.
Status: Operate
Mountie Park Campground Expansion and Site Services Upgrade
Upgraded some sites to 50 amp service and added six (6) new sites.
Status: Operate
108 Street Industrial – Corridor Rehabilitation
108 Street, Westlock, AB
Partners: MPE Engineering Ltd. and Knelsen Sand & Gravel
Status: Operate
Project Description: Phase Two is now completed Rail. This project continued the work from Phase One with upgrading the roadway, underground infrastructure, and curb/sidewalks along 108 Street. This project included the removal of the existing road surface and curb/sidewalks, installing a new sanitary water main, installing a new roadway structure, and installing new curbs and sidewalks.
Heritage Building HVAC Energy Efficiency and Exterior Upgrade
This project had two phases: the RTU and Ducting Upgrade and the Exterior Envelope Wrap.
Phase One Status: Operate
- Rooftop unit replacement on the south section of the Heritage Building, along with ducting upgrade and fire separation in the mechanical room.
- Start Date: October 2023
- Completion Date: January 2024
Phase Two Status: Operate
- The exterior envelope requires upgrading to increase facility efficiencies and improve on curbside appeal.
- Start Date: January 2024
- Completion Date: July 2024
2024 Annual Road Improvement Program
Rehabilitation of deteriorating road pavement structures by means of asphalt overlay and/or concrete replacement.
Status: Operate
Sand and Salt Storage
The Sand and Salt Storage Building contains the current salt/sand mix used in winter road maintenance and protects the material from the weather. This will reduce time and labour costs as staff will not have to thaw frozen materials. This efficiency will reduce production hours and reduce equipment wear and tear.
Start Date: August 18, 2022
Completion Date: December 2023
Public Works Shop and Cold Storage
The original facility was constructed in 1974.
Start Date: August 18, 2022
Anticipated Completion Date: February 2024
Partners: MPE Engineering and Atkinson Construction
Electric Vehicle (EV) Chargers
Westlock Powers Up with New Electric Vehicle Chargers!
Bringing Sustainable Energy to Our Community
A Milestone Achievement
Westlock is excited to announce the installation of three state-of-the-art Electric Vehicle (EV) chargers, available 24/7 to the public. This project, a significant leap towards sustainable development, has been realized through a grant from the Municipal Climate Change Action Centre (MCCAC) under its Electric Vehicle Charging Program (EVCP).
Strategic Locations for Maximum Benefit
- Westlock Rotary Spirit Centre (9603-100 Street)
- Heritage Building (10007-100 Avenue)
- Westlock Aquatic Centre (10605-104 Avenue)
These locations were chosen to enhance the convenience for EV users and to encourage exploration of our town's vibrant recreational areas, bustling downtown, and the municipal library.
Diverse Charging Options
Level Three Fast Charger at Rotary Spirit Centre: Ideal for quick charging needs. Charging rate: $20/hour.
Level Two Chargers at Heritage Building and Aquatic Centre: Perfect for longer visits. Charging rate: $2/hour.
Our Commitment to a Greener Future
This initiative reflects Westlock's dedication to sustainable development and reducing our environmental footprint. We thank the MCCAC for their support and look forward to future collaborations.
Polymanth Playground
Removal of existing equipment and replacement with improved play structures and amenities for a safe and enjoyable neighbourhood play area for years to come.
Grants, Funding Source: Funding approved through 2020-2024 Capital Plan.
Partners: Canadian Recreation Solutions
Start Date: May 24, 2022
Completion Date: August 11, 2022
Ribbon Cutting and Opening on August 11, 2022
Jubilee Arena Demolition
Jubilee Arena Demolition
Project Description: Initially slated for demolition in 2012, the Jubilee Arena structure degraded to an unsafe condition and was demolished in 2023.
Grants, Funding Source: General Surplus
Partners: MPE Engineering and Roadbridge Services Ltd.
Start Date: August 18, 2022
Completion Date: January 9, 2023
100 Street
This project scope includes the construction of an asphalt multipurpose trail along the south side of 100 Street Service Road from 108 Avenue to 113 street, as well as a concrete sidewalk along the east side of 113 Street from 100 Street Service Road to the Alberta Service Building. Pedestrian crossing signals were also added at the 108 Street/Highway 18 intersection. Most works were completed in 2021. Final trail work and landscaping were completed spring of 2022.
Lagoon Desludging
This project is to remove a build-up of sludge in the receiving cells at the sanitary sewage lagoon. This sludge builds up over many years and needs to be removed to improve the lagoon's operational efficiencies. Work started in April 2022 and is now complete.
Leak Detection and Monitoring System
In partnership with Bell Mobility and Echologics, a Mueller Water brand, this system will monitor hydrants throughout the community and provide data to pinpoint leaks and maintain our infrastructure in a new way. This will be a multi-year project with the installation of 50 sensors in 2022 and another 30 in 2023.
Storm Water Infrastructure Project
Grants, Funding Source: Alberta Community Resiliency Program and the Federal Investing in Canada Plan
Partners: MPE Engineering Ltd. and Pidherney’s Inc.
Start Date: February 2021
Completion Date: November 2021
Department Contact: Director of Operations
2021 Heritage Building Renovations
Heritage Building Renovations
10007-100 Avenue, Westlock, AB
This project was completed on time on June 15, 2021.
Grants, Funding Source: Funding approved through 2020-2024 Capital Plan.
Partners: Interworks Contracting Ltd.
Start Date: January 29, 2021
Completion Date: June 15, 2021